Progress view showing uncompleted section of Pilot Canal. Have 2,700' remaining. This dredge has advanced 3,000' since start of dredging on August 23. Average: 1,000' per week. Sarted at station 57/100. Now at 27/100. Total production to date: 658,489 yards. Overall length of canal: 9,000'. The dredge (William H. Black) completed approx.: 3,000' before this dredge taken over. Kansas City District, Channel Diversion Project.