View of progress made to date. Total advance since start of dredging: 3,000 ft. Total time: 3 weeks this date. Average 1,000' per week. Total production to date for job: 658.489 yds. Total dredge length of canal by both dredges: approx. 6,000'. Overall length of canal: 9,000'. Started station 57/100. Kansas City District, Channel Diversion Project.