Progress view showing uncompleted section of Pilot Canal. Have 2,700' remaining. This dredge has advanced 3,000' since start of dredging on August 23. Average: 1,000' per week. Sarted at station 57/100. Now at 27/100. Total production to date: 658,489 yards. Overall length of canal: 9,000'. The dredge (William H. Black) completed approx.: 3,000' before this dredge taken over. Kansas City District
Finish of dredging for first cut in Pilot Canal. The Earth plug is being left and will be blasted out to start river flow through new channel. Plug to be blasted October 4, 1952. The dredge (William H. Black) is at upper end of canal.
Showing dredge at station 7+00'. Station 6+50' tonight marked completion of dredging operations. A 50' wide plug will be left to be blasted out October 4, 1952. Kansas City District, channel diversion.
Showing pile dike that is being contructed across river channel made by flood to black and divery flow into new channel made by dredge. The second cut is just being started thru Pilot Canal from upper end. Kansas City District, channel diversion.
Showing shore line and discharge may be seen at left by house. To the right is the baffle plate discharge from the dredge (Black), which is dredging at upper end of Pilot Canal. This dredge is at station 11+20'. Total advance to date: 4,610'. Total yardage to date: 1,057,693. Kansas City District, channel diversion.
Dredge begins to back out of canal after completing first cut. Shown is plug that was left to separate the old and new channels that will be blasted out October 4, 1952. Dredge (William H. Black) at upper end. Kansas City District, channel diversion.
Dredging completed for first cut in Pilot Canal. Dredge is backing out of canal. On right bank is speaker's stand and cleared area being prepared for dedication and blasting of plug on October 4, 1952. Kansas City District, channel diversion.
Dredge as it advances forward through canal cut at station 17+50 after having advanced 4,000 feet with 1,700 feet remaining to be cut. Total production 859,260 cu. yards. Canal cut: 200 feet wide. Depth: 16 feet. Bank height: 17.5 feet. Kansas City District, channel diversion.
Showing dredge (William H. Black) headed directly into canal cut after it had dredged out opening. The (Ste. Genevieve) is at station 10+50'. Kansas City District, channel diversion.
The dredges (Ste. Genevieve) and (William H. Black) as they dredge opposite each other with 100 feet reamining to be dredged to mark completion of the channel diversion. An Earth wall 50' wide will be left and blasted out Saturday, October 4, 1052. Dredges now at stations 6+00' and 7+00'. Kansas City DIstrict, channel diversion.
Showing completed canal with dredge at station 11+30'. Total advance to date: 4,610'. Total yardage: 1,057,593. Kansas City District, channel diversion.
Cutting through the upper access road used by levvee contractor. At station 13+50'-3:00 P.M. View is towards the west, or river side. Also shown is the river channel that is to be diverted. Shoreline discharge can be seen. Kansas City District, channel diversion.