Position of dredge on completion of cut No. 2, which extended only 1800 ft. from upper end of canal. Dredge is getting ready for departure to St. Louis. Kansas City District, channel diversion.
Showing dredge at station 7+00'. Station 6+50' tonight marked completion of dredging operations. A 50' wide plug will be left to be blasted out October 4, 1952. Kansas City District, channel diversion.
Showing pile dike that is being contructed across river channel made by flood to black and divery flow into new channel made by dredge. The second cut is just being started thru Pilot Canal from upper end. Kansas City District, channel diversion.
Looking into Face of canal cut and showing remainder of canal to be cut. Roadway shown immediately across cut was used by levee contractor and was the cause of a 12-hour shutdown dispute. Kansas City District, Pilot Canal Project.
Looking aft. towards mouth of canal. Total advance has been 1,500 ft. Yardage: 325,000. Work started: Augues, 22, 1952. Kansas City District, Pilot Canal.
Showing shore line and discharge may be seen at left by house. To the right is the baffle plate discharge from the dredge (Black), which is dredging at upper end of Pilot Canal. This dredge is at station 11+20'. Total advance to date: 4,610'. Total yardage to date: 1,057,693. Kansas City District, channel diversion.
Dredge begins to back out of canal after completing first cut. Shown is plug that was left to separate the old and new channels that will be blasted out October 4, 1952. Dredge (William H. Black) at upper end. Kansas City District, channel diversion.
Looking forward to uncut section of Pilot Canal. At station 19+100. Total advance to date: 3,900'. Production to date: 894,260 yds. The canal cut ends at channel in background--distance of 1,800 feet. The river channel is the one cut by the flood last spring. Kansas City District, channel diversion.
Dredging completed for first cut in Pilot Canal. Dredge is backing out of canal. On right bank is speaker's stand and cleared area being prepared for dedication and blasting of plug on October 4, 1952. Kansas City District, channel diversion.
Dredge as it advances forward through canal cut at station 17+50 after having advanced 4,000 feet with 1,700 feet remaining to be cut. Total production 859,260 cu. yards. Canal cut: 200 feet wide. Depth: 16 feet. Bank height: 17.5 feet. Kansas City District, channel diversion.