Showing the dredge (William H. Black) which is placed at upper end of Pilot Canal and is dredging towards us. 1,350 feet separates the two dredges. (Black) started dredging operations at 12:30 P.M. This dredge is now cutting through the upper access road at station 13+50'. Kansas City District, channel diversion.
Opening that was blasted in plug to start flow of river through diversion channel. Head elevation approx. 2 feet. Towboat (Floyd) in Background. Kansas City District, channel diversion.
Pleasure craft (Markay II) - passing dredge (Mile 136.9). Shortly after passing dredge, this craft grounded heavily at Ste. Genevieve and unable to obtain assistance.
Dredge (William H. Black) as it dredges at upper end of canal. Making very slow progress in the gumbo. It is approx. station 600'. This dredge is at station 9+70'. The cut is now widened to 230' width. Has been 200'. Kansas City District, channel diversion.
Showing the Earth dike that now separates the present river channel and the channel that it is to be diverted into (lowerside). On upper side of dike is dredge (William H. Black). The dike will be dredged to 50' width, which will be blasted out. Dike is between stations 6+00' and 7+00'. Dredging completed tonight. In center, the blasting holes area being bored. Kansas City District, channel
View showing discharge line into new river channel made by flood last spring. Reveted bank shown will be for the third river channel that dredge is now cutting. Kansas City District, Pilot Canal Project.