View of progress made to date. Total advance since start of dredging: 3,000 ft. Total time: 3 weeks this date. Average 1,000' per week. Total production to date for job: 658,489 cu. yds. Total dredged length of canal by both dredges: approx. 6,000'. Overall length of canal project: 9,000'. Dredge now at station 27/100. Started at station 57/100. Kansas City District, Channel Diversion Project.
Approaching lift bridge at Kansas City when enroute from St. Joseph, Mo. To St. Louis. Dredge (William H. Black) is passing through bridge. Kansas City District.