View of progress made to date. Total advance since start of dredging: 3,000 ft. Total time: 3 weeks this date. Average 1,000' per week. Total production to date for job: 658,489 cu. yds. Total dredged length of canal by both dredges: approx. 6,000'. Overall length of canal project: 9,000'. Dredge now at station 27/100. Started at station 57/100. Kansas City District, Channel Diversion Project.
Vol. XXII. No. 48. Devoted to the Marine Profession, Yachting and Commercial Interests. Official Organ of the Western Rivers' Ferry Owners' Association.
United States Engineer Department. Placing abatis dike to close gap in driven pile dike. In chute between Establishment Island and Missouri shore near Brickeys.