View of progress made to date. Total advance since start of dredging: 3,000 ft. Total time: 3 weeks this date. Average 1,000' per week. Total production to date for job: 658,489 cu. yds. Total dredged length of canal by both dredges: approx. 6,000'. Overall length of canal project: 9,000'. Dredge now at station 27/100. Started at station 57/100. Kansas City District, Channel Diversion Project.
October 29, 1937. - Looking upstream from pilot house of Grafton. Graded bank and mattress weaving about station 219-00. Note curve on which Grafton entered below dike No.79.2L.