Leo Durocher and Buckey (sic) Harris (right), managers of the rival clubs, were all smiles before the game got under way. Harris pulled the surprise package out of the game in Vic Raschi who not only pitched two hitless innings but drove across two vital runs.
View of progress made to date. Total advance since start of dredging: 3,000 ft. Total time: 3 weeks this date. Average 1,000' per week. Total production to date for job: 658,489 cu. yds. Total dredged length of canal by both dredges: approx. 6,000'. Overall length of canal project: 9,000'. Dredge now at station 27/100. Started at station 57/100. Kansas City District, Channel Diversion Project.