View of progress made to date. Total advance since start of dredging: 3,000 ft. Total time: 3 weeks this date. Average 1,000' per week. Total production to date for job: 658,489 cu. yds. Total dredged length of canal by both dredges: approx. 6,000'. Overall length of canal project: 9,000'. Dredge now at station 27/100. Started at station 57/100. Kansas City District, Channel Diversion Project.
The dredges (Ste. Genevieve) and (William H. Black) as they dredge opposite each other with 100 feet reamining to mark completion of the canal to divert the river channel. An Earth wall 50 feet thick will not be dredged. It will be blasted out October 4, 1052. Dredges now at stations 6+00' and 7+00'. Kansas City District, channel diversion.
Showing completed canal and the plug that separates the old and new channels, which will be blasted out October 4, 1952. Stern of dredge (William H. Black) is shown. Kansas City District, channel diversion.
Looking down river at completed rock revetment that will serve as the west bank for the new channel. This rocked bank extends approx. 9,000 feet. Kansas City District, channel diversion.
Material removed from Pilot Canal being discharged into Rover channel that is going to be diverted. Dredging for canal will be completed tonight. Dredge is at station 7+00'. The earth plug to be blasted is at station 6+50'. Kansas City District, channel diversion.
Dredging of first cut completed and dredge is about halfway of canal length as it backs out. View is to lower end of canal. Kansas City District, channel diversion.
Cutting through the upper access road used by levvee contractor. At station 13/50'-3:00 P.M. This is looking towards St. Joseph. Kansas City District, channel diversion.
View of crowd on bank of the Pilot Canal during ceremonies prior to blasting of plug that opened the diversion canal. Kansas City District, channel diversion.
The dredges (Ste. Genevieve) and (William H. Black) as they dredge opposite each other with 100' separating dredges to mark completion of the Diversion Channel Project. An Earth wall 50' thick will not be dredged. It will be blasted out. Dredges at station 6+00' and 7+00'. Kansas City District, channel diversion.
Showing laying of advance shore pipe. A new line is layed every 750 ft. of dredge advance. Shown also is section of almost completed levee. This levee is the reason that the discharge line has to be so long. River channel made by flood can be seen in extreme background. Station 1,800 feet. Kansas City District, channel diversion.
View of progress made to date. Total advance since start of dredging: 3,000 ft. Total time: 3 weeks this date. Average 1,000' per week. Total production to date for job: 658.489 yds. Total dredge length of canal by both dredges: approx. 6,000'. Overall length of canal: 9,000'. Started station 57/100. Kansas City District, Channel Diversion Project.
Opening that was blasted in plug to start flow of river through diversion channel. Head elevation approx. 2 feet. Towboat (Floyd) in Background. Kansas City District, channel diversion.
Showing the Earth dike that now separates the present river channel and the channel that it is to be diverted into (lowerside). On upper side of dike is dredge (William H. Black). The dike will be dredged to 50' width, which will be blasted out. Dike is between stations 6+00' and 7+00'. Dredging completed tonight. In center, the blasting holes area being bored. Kansas City District, channel
Showing levee construction and Equipment, which is almost completed. Moving some of equipment out today. River in background is channel that was cut by flood last spring and it is to be re-routed into a new channel that the dredge is making the pilot canal for. Station 18+100'. Kansas City District, channel diversion.
Dredge as it advances through canal cut at station 17+50. Total advance to date: 4,000 feet. Total production 859,260 cu. Yards. Approx 1,700 feet to dredge yet. Kansas City District, channel diversion.
Showing Governor Forrest Smith on speaker's stand during ceremonies prior to blasting of plug that opened diversion channel. Kansas City District, channel diversion.
Dredge (William H. Black) as it starts in at upper end of canal. Dredging at an angle to provide opening. (Ste. Genevieve) is at station 10+50'. Kansas City District, channel diversion.